Durban port crisis: medicines, jobs and exports cannot wait three more months

Issued by Dr Chris Hunsinger MP – DA Spokesperson on Transport
26 Nov 2026 in News

The Democratic Alliance (DA) is deeply concerned that ships are waiting up to 20 days to berth at the Durban Gateway Terminal, the terminal that handles almost half of South Africa’s containerised freight. This is no longer a logistics problem. It is a crisis for patients, for workers and for every South African paying more at the till.

The human cost is already visible. The Minister of Health has told Parliament’s Portfolio Committee on Health that medicines are stuck at anchor off Durban while the national list of medicines at risk of running out has more than doubled since May, to 184 products. Around 95% of our medicines arrive by ship. A patient waiting for antibiotics or chronic medication should never be at the back of a shipping queue.

The economic damage is spreading just as fast. Automotive suppliers are paying for emergency air freight to keep assembly lines running. Citrus trucks have waited up to 30 hours to deliver refrigerated containers. Shipping lines are adding congestion surcharges, and thousands of containers have been diverted to other ports. Every one of these costs ends up in the price of goods.

The DA supports private sector participation in our ports. It is the only way to fix decades of under-investment at Transnet. But partnership must come with performance and accountability. By the Minister of Transport, Barbara Creecy’s own account, the terminal ran 21% above target in its first six months. The collapse followed the switch to a new terminal operating system in August, introduced just ahead of the peak festive season, while straddle carriers and cranes remained in short supply.

What concerns us most is the lack of consequences. In a written reply to Parliament that was published on 30 October, Minister Creecy confirmed that the transitional period was quietly extended to December 2026, that no enforcement action had been taken, and that Transnet is unable to estimate what the congestion is costing the economy. You cannot manage what you do not measure.

The Minister has now given the operator three months to improve. However, the country cannot simply wait and hope.

The DA calls for:

1. A public recovery plan with weekly targets for anchorage times, crane moves and truck turnaround, published every week until the backlog is cleared.

2. Enforcement of the performance terms in the concession agreement, and disclosure of those terms to Parliament’s Portfolio Committee on Transport.

3. Guaranteed priority for medicines and critical inputs, with the Departments of Health and Transport reporting publicly on every priority container until it is released.

4. An urgent briefing to the Portfolio Committee by Transnet, the Ports Regulator, and the terminal operator.

5. Rail capacity to move containers inland, so that cleared cargo does not simply move the queue from the quay to the N3.

The DA will keep holding the Minister, Transnet, and the operator to account until the Port of Durban works for the people who depend on it.