Donkies River Bridge Rebuilt

09 Oct 2019 in Where We Govern

The DA-led Breede Valley municipality listened to the pleas of the Steenvliet community and upgraded the Donkies River bridge in Touwsriver. The old structure was not built to be used as a pedestrian structure and was a safety hazard for residents wanting to cross to the other side.

Alpha Civil, a contractor based in Worcester, was appointed to construct the new bridge which now offers a much safer and more convenient crossing for pedestrians. Construction started in June 2019 at a cost of R1,96 million and was completed in October 2019. The project created job opportunities for locals during the construction phase.

Mayor Antoinette Steyn said that this project is just one way of showing residents that the DA-led Breede Valley municipality is responsive to the needs of the community.